Forge Road Water Main Connector Project

The Forge Road Water Main Connector Project was began in November, 2014 and completed (due to weather delays) in May, 2015.

The project financed by Water Bonds and at a cost of $407,570 constructed approximately 5,100 lineal feet of water main from M-35 west to Forge Road - providing an alternate water supply feed for Negaunee Township's Water System.



Click Here - PowerPoint Picture Slideshow of Forge Road Water Project